To Do

Well, it’s not a formal project plan, but here are the numerous things that we need to do for our remodel/renovation. They are somewhat in order, but not necessarily. I’ll add things here as we decide to add more. It always happens!

  1. Architectural Plans
  2. Detailed site survey
  3. Meet with neighbors to make sure we’re not going to piss them off.
  4. Select contractor
  5. Collect bids
  6. Collect straggling bids for the items that are still unknown And I don’t want any more bids. Out of money, ya know!
  7. Structural Engineer Design
  8. Sign Letter of Authorization with Contractor
  9. Get Financing (which required its own set of steps)
  10. Submit plans for building permit/zoning review
  11. Trees Removed & Milled
  12. Move out of house into temporary apartment
  13. Demo the house (Just parts that are being replaced)
  14. Asbestos Testing – All Clear!
  15. Demo the backyard, side covered patio, fence & retaining walls, concret
  16. Remove storm windows – In Progress
  17. Rolloff delivered
  18. Strip & sand beams throughout house – In Progress
  19. Strip mahogany trim – In Progress
  20. Get temporary power
  21. Demo closets (being reconfigured)
  22. Lead Paint Testing
  23. Remove interior doors
  24. Strip Interior Concrete Block – In Progress – My never ending hell
  25. Strip Exterior Concrete Block – In Progress – Fun with power washer
  26. Excavate site
  27. Replace sewer pipe
  28. New connection from sewer pipe to plumbing
  29. Rough grading
  30. Finish selecting fixtures & finishes (sink, faucet, etc.)
  31. Geotech soil samples
  32. Surveyors stake footers
  33. Footers (form & pour)
  34. Install Hielical Piers
  35. Independent Structural Letter
  36. Order Nanwall – big west facing window wall
  37. Order rest of windows
  38. Foundation
  39. Backfill foundation
  40. Fence Installation
  41. Build new gate
  42. Waterproofing/Drainage
  43. Backfill/Fine Grading /Compaction Testing
  44. Remove oak floors from existing living room/dining room (flooring to be relocated)
  45. Framing
  46. Concrete Block
  47. Roof Tear Off
  48. Redeck roof/ceiling
  49. Prewiring – CAT6/Coax
  50. Roofing
  51. Electric – In Progress – Rough-in Complete
  52. Plumbing – In Progress – Rough-complete
  53. HVAC system – In Progress - Rough-in complete
  54. Stain Ceiling T&G and Beams – In Progress
  55. Fascia & Downspouts
  56. Install Exterior Siding
  57. Install Windows
  58. Replace glass for historical windows
  59. Hang drywall / wood walls
  60. Interior Trim Work
  61. Install Cork Flooring
  62. Remove 1 million twisted nails from existing oak flooring
  63. Refinish oak flooring in existing house
  64. Install phone/cable outlets & punch-downs
  65. Reconnect Permanent Electric Service
  66. Reconnect Phone Service
  67. Reconnect Cable Service
  68. Build cabinets – In progress
  69. Install cabinets
  70. Install appliances
  71. Install countertops
  72. Repair existing masonry
  73. Repair/clean interior brick stairway
  74. Repair/Clean-up damage from glue flying off of roof in wind storm into driveway, concrete block wall, new concrete block planter and garage door. Big Mess!
  75. Build new stairway rails
  76. Stain mahogany trim, wall panels, kitchen cabinets, bathroom cabinets
  77. Enclose 3rd bedroom & build out closets
  78. Install new toilets
  79. Gut old bathroom cabinets
  80. Install bathroom sink/cabinets/fixtures
  81. Install Lighting
  82. Interior Painting
  83. Exterior Painting
  84. Hang Doors
  85. Exterior flatwork (patios, driveway) – Yea, that’s not gonna happen this year!
  86. Replace wood on garage door.
  87. Build out master closet shelving
  88. Design study built-in’s. (May Will defer to later)
  • Print this article!
  • Digg
  • Google Bookmarks
  • Twitter
  • Yahoo! Bookmarks

Comments on this entry are closed.